Indexed as:
Laredo Development Ltd. v. I.R. Capital Corp. (B.C.C.A.)
[1993] B.C.J. No. 2311
Vancouver Registry No. CA013918


BRITISH COLUMBIA COURT OF APPEAL


Between

Laredo Development Ltd.

Respondent, Appellant by
Cross-Appeal, (Plaintiff)

And

I.R. Capital Corporation 

Appellant, Respondent by
Cross-Appeal, (Defendant)

Vancouver, British Columbia
Toy, Taylor and Rowles JJ.A.

Heard: October 20 and 21, 1993.
Judgment: filed November 17, 1993.
(39 pp.)

Counsel:

Counsel for the Appellant:  George E.H. Cadman and Brenda Brown.
Counsel for the Respondent:  Richard H. Hamilton and James A. Hall.


 1      TOY J.A. (for the Court, dismissing the appeal):— On December 12, 1988, the plaintiff, Laredo Development Ltd. (Laredo), and the defendant, I.R. Capital Corporation (I.R. Capital) entered into an agreement with respect to the purchase and sale of a 49-unit condominium development in Richmond, British Columbia, which was then in its earliest stage of construction.  The agreement provided, firstly, for an option to purchase the whole project; secondly, that upon the exercising of the option the parties would be deemed to have entered into a binding contract of purchase and sale; and, thirdly, on completion of construction and issuance by the Municipality of Richmond of a final building inspection certificate, seven days thereafter the transaction would be completed by payment of the balance of the purchase price and transfer of title to the property.  The option was exercised by Laredo.  On June 30, 1989, the two responsible officers of the parties, namely Mr. Rogowski, on behalf of I.R. Capital, and Mr. Richert, on behalf of Laredo, orally agreed to vary a term of the agreement extending a completion date to August 31, 1989.  The trial judge concluded that prior to the date for the completion of the sale and purchase, I.R. Capital had repudiated the agreement.  He ordered I.R. Capital to return to Laredo the $700,000 it had paid when it exercised the option and to pay Laredo $429,000 in damages.  I.R. Capital has appealed the judgment and Laredo has cross-appealed on the quantum of damages awarded.

 2      The judgment of the trial judge, Mr. Justice Braidwood, is now reported:  17 R.P.R. (2d) 11.  However, before addressing the issues raised on these appeals, I propose to summarize some of the pertinent facts in chronological order and set out most of the terms of the written agreement between the parties.

 3      The first three clauses of the agreement between the parties dated December 12, 1988, deal with the initial phase of the agreement, namely the exercising of the option. This entailed two payments of $100,000 and $600,000 which, if paid, were to be credited to the full purchase price for the project of 7.1 million dollars.  Although there was an issue raised at trial whether those funds had been fully paid, no such issue has been raised on this appeal.

 4      Clauses 3 to 11 inclusive and Clause 16 have bearing on the issues raised on these appeals and I now produce those clauses in their entireties:

3.

EXERCISE


3.1  This Option may be exercised at any time up to but not after the hour of 11:59 p.m. on February 28, 1989 (the "Term") by the Optionee, its solicitors, agents or assigns, delivering a notice in writing to the Optionor in the manner provided for in section 12 together with a non-refundable payment to the Optionor of SIX HUNDRED THOUSAND DOLLARS ($600,000.00) (the "Second Option Payment").

3.2  If this Option is exercised by the Optionor, the Optionor and the Optionee shall be deemed to have entered into a binding contract for the sale and purchase of the Lands on the terms and conditions contained in this Agreement.


4.

PAYMENT OF PURCHASE PRICE


4.1  If, as and when this Option is exercised by the Optionee the Purchase Price shall be paid as follows:

       4.1.1  by crediting in full to the optionee the amount of the First Option Payment and the Second Option Payment;

       4.1.2  the balance of $6,400,000 SIX MILLION FOUR HUNDRED THOUSAND to be paid by the Optionee by certified cheque to the solicitors for the Optionor on the Completion Date as hereinafter defined.


5.

COMPLETION


5.1  If, as and when the Option is exercised by the Optionee, the sale of the Lands shall be completed by the parties hereto on a date occurring 7 business days after the date on which the Municipality of Richmond has issued a Final Building Inspection certificate for the Development (hereinafter "Completion Date").

5.2  On the Completion Date the Optionor shall deliver to the Optionee:

       5.2.1  a Transfer of an Estate in Fee Simple, transferring the Lands to the Optionee free and clear of all liens, charges and financial encumbrances of any kind except for:


(a)

the legal notation under the Aeronautics Act (Canada) described in recital A;

(b)

subsisting encumbrances in the nature of utility easements, rights-of-way, restrictive covenants and similar encumbrances;

(c)

subsisting conditions, provisos, restrictions, exceptions and reservations, including royalties, contained in the original grant and contained in any other grant or disposition from the Crown;

(d)

such further encumbrances in the nature of utility easements, rights-of-way, restrictive covenants and similar encumbrances, required by public authorities to be placed against title to the Lands from the date of this Option Agreement to the Completion Date and which do not materially effect the marketability of the Lands; and

(e)

the encumbrances shown on Schedule A hereto (the "Permitted Encumbrances";


all in a form satisfactory to the solicitors for the Optionee, and in a form acceptable for registration in the appropriate Land Title Office.

       5.2.2  registrable discharges of the Permitted Encumbrances or undertakings from the Option's solicitors to discharge the Permitted Encumbrances with the net sale proceeds;

5.3  The Optionee shall place the cash portion of the Purchase Price after adjustments payable to the Optionor in trust with its "solicitors prior to the Completion Date for delivery to the Optionor immediately upon filing for registration in the appropriate Land Title Office of the Transfer of an Estate in Fee Simple conveying title to the Lands to the Optionee free and clear of all liens, charges and financial encumbrances except for the charges described in section 5.2.1.


6.

FAILURE TO COMPLETE


6.1  Once the within Option has been exercised, if the Optionee fails to pay the balance of the Purchase Price on the Completion Date this Agreement shall be null and void and the Optionor shall be entitled to retain and keep both the First Option Payment and the Second Option Payment as consideration paid to the Optionor for granting the Option.


7.

ADJUSTMENT AND POSSESSION


7.1  All adjustments for taxes, rents and any other items normally the subject of adjustment for the Lands shall be made on the Completion Date, which date is hereinafter called the "Adjustment Date: and on the Adjustment Date the Optionor shall also deliver to the Optionee vacant possession of the Lands unless specific alternate arrangements have been made in writing between the parties hereto.


8.

COSTS OF TRANSFER


8.1  The Optionee shall bear all costs of preparing and registering the Transfer of an Estate in Fee Simple to the Lands, the Optionor shall be responsible for and shall pay all costs of clearing title to the Lands.


9.

CONSTRUCTION OF THE DEVELOPMENT


9.1  The Optionor covenants that it shall construct the Development in a good and workmanlike manner using materials of a quality that is normally accepted by the construction industry in developments that are similar to the Development in accordance with the National Building Code and all municipal requirements.  The Optionor shall be entitled to make such changes to the recommended or required by such consultants or any governmental authority having jurisdiction over the Development or as the Optionor may deem appropriate or necessary provided that the Development is not thereby substantially altered and provided that the Optionee consents to such changes, such consent not to be unreasonably withheld.


10.

COMPLETION OF THE DEVELOPMENT


10.1  The Optionor shall complete construction of the Development such that the Completion Date shall occur on or before June 30, 1989.  If the Completion Date has not occurred on or before June 30, 1989, the Optionor may extend the Completion Date up to July 31, 1989 without cost or penalty to the Optionor.

10.2  If either party is bona fide delayed or hindered in or prevented from the performance of any term, covenant or act required hereunder including, in the case of the Optionor, from completing construction of Development by the Completion Date or any extension thereof, by reason of strikes, labour troubles; inability to procure materials or services; power failure; restrictive governmental laws or regulations; riots; insurrection; sabotage; rebellion; war, act of God; or other reasons whether of a like nature or not which is not the fault of the party delayed in performing work or doing acts required under the terms of this Agreement, then the performance of that term, covenant or act or the completion of construction is excused for the period of the delay and the party delayed will be entitled to perform that term, covenant, act or the completion of construction within the appropriate time period after the expiration of the period of the delay.

10.3  If the Completion Date has not occurred on or before December 31, 1989, this Agreement shall be null and void and all deposit monies shall be returned forthwith to the Optionee.


11.

TIME OF THE ESSENCE

       11.1 Time shall be of the essence in this Agreement.

 5      The trial judge found that it was the intention of Laredo to sell the property it was acquiring from I.R. Capital to R.I.A. Properties International Ltd. (R.I.A.) for the sum of $7,815,000.  Laredo concluded an agreement in writing with R.I.A. on the same day it signed the agreement with I.R. Capital, the terms of which substantially paralleled the arrangements that Laredo had made with I.R. Capital.  The Laredo-R.I.A. agreement contained this clause:

4)

The Completion Date shall be on the 7th business day after the Municipality of Richmond has approved occupancy of the Development.  If the Completion Date has not occurred on or before June 30, 1989 the Vendor shall be responsible to the Purchaser for any lost income the Purchaser may suffer.  If the Completion has not occurred on or before December 31, 1989, unless the parties agree otherwise, the agreement shall be null and void and all deposit monies shall be returned to the Purchaser.

 6      As a consequence of the agreement that Laredo had made with R.I.A., throughout the ensuing months after December 12, 1988 it was R.I.A., not Laredo, that engaged itself in the business of organizing the sales of the 49 condominium units to various individual purchasers in Hong Kong.

 7      In June 1989, it became apparent to both parties that construction would not be completed when anticipated.  On June 29, 1989, Mr. Rogowski, on behalf of I.R. Capital, wrote to Laredo notifying it that pursuant to Clause 10.1 of the agreement, I.R. Capital intended to extend the completion date to July 31, 1989.  A further extension to August 31 on reasonable terms and conditions was requested.

 8      At a breakfast meeting on June 30, 1989 an oral agreement was reached regarding an extension.  A letter dated June 30, 1989 was sent by I.R. Capital to Laredo which was intended to reflect the terms of the oral agreement reached earlier in the day.  The letter read, in part, as follows:

Further to our meeting of today's date, we wish to confirm the following regarding the captioned Option Agreement:


1.

Extend the completion date to July 31, 1989, as per clause 10.1,

2.

Further 30 day extension of the completion date to August 31, 1989, for the sum of $50,000. payable to Laredo Development Ltd.  Please acknowledge your acceptance by signing this letter.

 9      The letter was signed by Mr. Rogowski on behalf of I.R. Capital and on July 4, 1989 by Mr. Richert on behalf of Laredo.  The $50,000 was subsequently paid by I.R. Capital to Laredo.

 10      Between July 25 and August 6 and between August 18 and August 28, Mr. Richert was in Hong Kong for the purpose of ensuring that the arrangements R.I.A. had in place for the resale of the property would be completed on time for it was relying upon the funds that it would receive from the resale of the individual units to discharge at least in part its obligations to I.R. Capital.

 11      On August 29, 1989, Mr. Rickert returned from Hong Kong.  On August 30 he received, by courier, the following letter from I.R. Capital, which was signed by Mr. Rogowski:

What's going on re the deal -- 49 townhouse units to complete August 31, 1989??

Please respond immediately.

 12      On August 30, 1989, I.R. Capital's solicitor, Mr. Panton, was instructed by Mr. Ragoski to insist upon the transaction closing on the next day.

 13      I.R. Capital received final building inspection approvals and certificates on the morning of August 31, 1989.

 14      On August 31, 1989, I.R. Capital tendered certain documents, including an executed transfer of the property, and demanded that Laredo complete the purchase that day.

 15      On September 1, 1989, Mr. Panton wrote to Mr. Siebold, the solicitor for Laredo, demanding return of the executed transfer.  The transfer was returned.

 16      On September 30, 1989, Laredo commenced the present action claiming specific performance of the agreement and in the alternative damages.  On October 13 an order was made requiring Laredo to post security of $1,500,000 by October 17 to preserve its lis pendens filed against the property.  Laredo successfully applied to extend the time to October 19, but the required security was not posted.  By letter dated October 18, 1989, from the solicitor for Laredo to the solicitor for I.R. Capital, Laredo notified I.R. Capital it would not be posting the required security and that it would be pursuing its claim for damages.

 17      When the action came on for trial it was common ground that I.R. Capital had individually sold all but three of the 49 condominium units for $7,392,800.  If the last three units were to sell for $160,000 each, I.R. Capital realized, or could realize, something in excess of 7.8 million dollars as opposed to the 7.1 million it would have received had the transaction with Laredo been completed.

 18      The grounds of appeal stated in the appellant's factum are:

1.

The Learned Trial Judge erred in finding that the Appellant (Defendant) I.R. Capital Corporation was not willing to complete the transaction in question; that is, that it had repudiated the Agreement.

2.

The Learned Trial Judge erred in finding that the date set for completion of the transaction in question was September 11, 1989 rather than August 31, 1989.

3.

The Learned Trial Judge erred in finding that the Respondent (Plaintiff) Laredo Development Ltd. was ready, willing and able to complete the transaction in question, or, alternatively, need not have been by reason of I.R. Capital's supposed repudiation.

4.

The Learned Trial Judge erred in finding that the Respondent (Plaintiff) Laredo Development Ltd. was entitled not only to a return of the deposit of $700,000.00, but also to damages in the further amount of $429,000.00.

 19      At the apparent invitation of counsel for Laredo in the court below, the trial judge analyzed the rights and obligations of the parties on two bases, firstly, on the assumption that the date for completion of the transaction was August 31, 1989, and, secondly, on the assumption that the date of completion of the transaction was seven business days later, namely September 11, 1989.

 20      I am of the firm opinion that the more appropriate approach for purposes of this appeal is to interpret the terms of the written agreement of December 12, 1988 as varied or modified by the oral agreement struck by Mr. Rogowski and Mr. Richert at their meeting on June 30, 1989. Accordingly, I propose to deal with Ground 2 first.

DID THE TRIAL JUDGE ERR IN FINDING THE DATE SET FOR COMPLETION OF THE TRANSACTION WAS SEPTEMBER 11, 1989?

 21      Here counsel for I.R. Capital argued that on a plain reading the letter agreement of June 30, 1989, and the option agreement of December 12, 1988, clearly determined that the completion date for closing purposes was August 31, 1989. In this connection he relies on the Completion Date in the option agreement as being a defined term.  I do not find the cases counsel for I.R. Capital cited as being helpful.  His final submission on this ground of appeal was that the failure of I.R. Capital to deliver a final building inspection certificate seven days prior to August 31, 1989, would serve only to trigger a penalty under Clause 10.1.  The "Completion Date" would not be altered.

 22      The foregoing submissions, in my view, do not address the trial judge's analysis of the evidence of the witnesses to the June 30, 1989 meeting, nor the trial judge's interpretation of the written agreement as varied by the verbal agreement made by Mr. Rogowski and Mr. Richert on behalf of the two parties to this action.

 23      I start from the following overview of the terms of the agreement of December 12, 1988.

 24      The first phase, or facet, of the agreement, namely Clauses 1, 2 and 3, provide for the granting of the option and the two option payments of $100,000 and $600,000 which Laredo exercised by February 28, 1989.  According to Clause 3.2 the exercising of that option changes the relationship of the parties by deeming them to have entered into a binding contract of purchase and sale.  Clause 6 provides that if Laredo fails to complete the transaction I.R. Capital will be entitled to keep the $700,000 as consideration for the granting of the option.

 25      The second facet of the agreement relates to I.R. Capital's obligation to construct the 49-unit townhouse development in accordance with specified architectural drawings and engineering and electrical specifications which, according to Clause 9, would be constructed "in a good and workman like manner" and "in accordance with the National Building Code and all municipal requirements."  One such municipal requirement is the satisfactory compliance with the development's building permits and the issuance of a final building inspection certificate for all 49 units comprising the development.  According to Clause 5.1, the transaction must be completed on a date occurring seven business days after the issuance of the final building inspection certificate.  However, that clause gives no clue as to the date when the construction of the project was required to be completed.  To determine that date one must refer to Clauses 10.1, 10.2 and 10.3.

 26      The opening words of Clause 10.1 "The Optionor shall complete...before June 30, 1989", at first blush, have an imperative connotation.  The next sentence gives the Optionor (I.R. Capital) the right to extend the Completion Date up to July 31, 1989, without cost or penalty, clearly bestowing upon I.R. Capital the unilateral benefit of an additional month within which to complete construction, without exposing itself to a claim by Laredo for any costs it might incur as a result of any delay in completion of the transaction past June 30, 1989.

 27      Clause 10.2 is another provision primarily for the benefit of I.R. Capital which would protect it in the event that construction delays were caused by events beyond its control.  Lastly, Clause 10.3 places a final date within which the construction of the project must be completed, the final building inspection certificate must have issued and still give Laredo seven business days before December 31, 1989 within which to fulfill its obligation to complete the transaction.  If these events have not occurred in a timely fashion, according to Clause 10.3, the whole agreement shall be null and void and the $700,000 paid as an option payment should be returned by I.R. Capital to Laredo.  Clause 10.3 is of obvious benefit to both I.R. Capital and Laredo.

 28      In summary, properly interpreted the combined effect of reading Clauses 5.1, 10.1, 10.2 and 10.3 together is that the parties agreed as follows:

1.

The date of completion of construction of the project would be determined by an independent third party, namely the Municipality of Richmond when it issued its final building inspection certificate after construction of the 49 condominium units had been completed.

2.

I.R. Capital's target date for completion of construction was seven business days before June 30, 1989.

3.

I.R. Capital had the unfettered right to invoke an extension for the completion of construction, that is the issuance of the municipality's final building inspection certificate, to seven business days before July 31, 1989.

4.

That after July 31, 1989, and up to seven business days before December 31, 1989, I.R. Capital had the continuing right to insist upon Laredo completing the transaction providing the final building inspection certificate issued seven business days before December 31, 1989, subject to I.R. Capital satisfying Laredo's claims for its costs incurred as a result of I.R. Capital's delays in not completing the transaction by July 31, 1989.

 29      In short, I.R. Capital, on December 12, 1988, did not commit itself to a firm date for completion of construction of the project, nor completion of the transaction.  The agreement gave to I.R. Capital substantial flexibility in an area that usually defies accurate predictability.

 30      The third and final phase of the agreement of December 12, 1989, following the issuance of the final building inspection certificate, was completion of the transaction, namely the sale of the land, together with its improvements.  The relevant provisions are to be found in Clauses 4.1, 5.1, 5.2 and 5.3.  As the object of the exercise from Laredo's perspective was to sell, or arrange to have sold, the 45 condominium units -- or as many of them as could be sold -- it is not surprising, in view of the flexibility that was accorded to I.R. Capital in the timing of completion of construction, that Laredo had reserved for its benefit seven business days after the issuance of the final building inspection certificate within which to get its affairs in order to successfully perform its completion obligations.

 31      I turn now to consider the event that occurred on June 30, 1989.

 32      Prior to that date, by letter of June 29, 1989 sent by I.R. Capital to Laredo, I.R. Capital had exercised its right to extend the Completion Date pursuant to the second sentence of Clause 10.1 from June 30 to July 31, 1989.  The letter further requested an extension to August 31, 1989 "on reasonable terms and conditions".  That request resulted in a meeting of the two principals, Mr. Rogowski and Mr. Richert. Also present at the meeting was Mr. Porter who at that time was in the employment of I.R. Capital.

 33      The trial judge reviewed the evidence given by Mr. Richert which evidence was confirmed by the effect of the evidence of Mr. Porter.  Mr. Richert's evidence in summary was:

The need for the extension was the fact that construction of the project was not on target and that Mr. Rogowski requested an extension of 15 days, in addition to an extension to July 31, 1989, contemplated as the extension allowed under the agreement.  At the meeting, Mr. Richert expressed his view that 15 days would not be enough time in which to complete the construction, for he had inspected the job, and suggested that August 31, 9189, would be more appropriate.  He further suggested that $50,000 would be an appropriate consideration for the extension, and this was agreed to by Mr. Rogowski.

       Mr. Richert further testified that, at that time, they did not have a discussion concerning a final completion date in terms of the completion of the documentation and the transferring of the funds. The whole discussion revolved around when the project would be finished in terms of construction, and what was the likely time frame in which the municipality would be issuing the completion certificate.

 34      In reviewing the testimony of Mr. Rogowski concerning the discussion at the June 30, 1989 meeting, the trial judge, in paras. 34 and 35, stated this:

       I find the evidence of Mr. Rogowski as it relates to the arrangements surrounding the oral extension agreement to be confusing and inconsistent.  He was unable to distinguish in his evidence between the conclusions that he reached and the particulars of what the parties said at any particular time or place.  He had made up his mind that Mr. Richert would not be able to complete on time, and he acted at all times in accordance with that belief.  His evidence concerning the breakfast meeting at the Delta Hotel is inconsistent with the evidence given by Mr. Porter and Mr. Richert.  He insists that the arrangements were made weeks, if not months, prior to the meeting, and that the meeting and the later letter only confirmed what he already had agreed upon much earlier.  He further testified that what had been agreed upon was that the construction, the completion and the transfer of the moneys should all be completed on August 31, 1989.  He was not able at any time to articulate any conversation that would lead one to conclude what was the actual arrangement between the parties.

       His evidence on discovery did not indicate that the completion for the transaction was to be on August 31, 1989.  It reads as follows:


Q.

All right.  What were the terms of that agreement, sir, that you would extend the completion of construction date to August 31?

               A. Yes.

 35      Later in his reasons, when considering the evidence on the basis of the second assumption proposed by counsel for Laredo, the trial judge addressed the question whether the closing date for the transaction was September 11, 1989.  I agree with the trial judge's interpretation of the combined effect of the provisions of Clauses 5.1, 10.1 and 10.3.  I have reviewed all the evidence of Messrs. Rogowski, Richert and Porter, and have come to the same conclusion as the trial judge -- that the purpose of the verbal agreement of June 30, 1989 was to modify the second sentence of Clause 10 to read in these words:

"If the completion date has not occurred on or before June 30, 1989, the Optionor may extend the completion date up to August 31, 1989, without cost or penalty to the Optionor."

 36      My reading of the evidence of Mr. Rogowski leads me to conclude that, if believed, from the time of the meeting on June 30, 1989, the terms of the agreement of December 12, 1988 had been altered by substituting for the elaborate scheme provided in Clauses 5.1, 10.1, 10.2 and 10.3 a firm, fixed date for completion of the transaction by August 31, 1989.  My conclusion is supported by examining Mr. Rogowski's conduct and his instructions to his new solicitor, Mr. Panton, late in the day of August 30, 1989, his dealings with Mr. Richert on the morning of August 31, 1989, and his further instructions to Mr. Panton to insist upon precise compliance with the terms of a letter sent by the solicitor for I.R. Capital to the solicitor for Laredo on that date.

 37      It was Mr. Rogowski's view that after the June 30, 1989 oral agreement modifying the December 11, 1988 written agreement, I.R. Capital was no longer obliged to give Laredo seven business days after the final building inspection certificate issued to complete the transaction, or that I.R. Capital had to have obtained the municipality's final building inspection certificate by the date then set for completion of the transaction.  Mr. Panton, I.R. Capital's solicitor at the time of completion, confirmed that those were Mr. Rogowski's instructions to him prior to the closing date.

 38      Under cross-examination Mr. Rogowski responded to questions by counsel for Laredo as follows:

Q.

Thank you.  That wasn't my question.  My question was when you met at the Airport Inn and Mr. Richert and Mr. Porter, did you tell them that under this extension there is no requirement for a building inspection certificate?

A.

We did not discuss about the building inspection.

Q.

When you met at the Airport Inn, did you have this option agreement in front of you?

A.

I don't remember, sir.

Q.

You didn't, did you?

A.

I don't remember, sir.  This agreement was drafted by Ross Porter.

Q.

When you met at the Airport Inn, was there any discussion amongst you and Mr. Richert and Mr. Porter about taking out paragraph 5.1 of the agreement?

A.

When we met at the Airport Inn, we only came to discuss the new final deal that's gonna be completed on August the 31st.  We never went back to the agreement.  They -- we give it -- we exercise our option.  We discussed the money, and that's all we did in the meeting. We never went back to that agreement.  It was like almost a new deal was struck and that's what we struck.

Q.

Thank you.  Is the answer to my question, no, we did not discuss paragraph 5.1?

A.

We did not discuss none of the option.

Q.

And at that meeting that you had with Mr. Richert and Mr. Porter, did you discuss paragraph 10.3 of the option agreement.

A.

Sir, we did not discuss the option.

Q.

So, the answer to my question was, no, we did not discuss paragraph 10.3?

A.

No. We did not.

 39      Those responses by Mr. Rogowski, for me, provide additional evidence supporting the trial judge's conclusions on the extent of the oral modification of December 12, 1988 agreement that occurred on June 30, 1989.  In light of there being no discussion about these vital matters, I do not understand how Mr. Rogowski could possibly have concluded that Mr. Richert was abandoning or waiving either the requirement for the issuance of the final building inspection certificate or the seven business day period provided within which Laredo could prepare for closing the transaction.  It also appears illogical, to me, that by setting a firm, fixed date for completion of the transaction that I.R. Capital would lose the benefit of both Clauses 10.2 and 10.3.

 40      In summary on this ground of appeal I am satisfied that the trial judge's conclusion that Laredo's obligation to complete would arise on September 11, 1989, was amply supported by the evidence and I agree with his interpretation of the written agreement as orally modified.  I would reject the second ground of appeal.

 41      I turn now to a consideration of the first and third grounds of appeal articulated in the appellant's factum:

1.

The Learned Trial Judge erred in finding that the Appellant (Defendant) I.R. Capital Corporation was not willing to complete the transaction in question; that is, that it had repudiated the Agreement.

3.

The Learned Trial Judge erred in finding that the Respondent (Plaintiff) Laredo Development Ltd. was ready, willing and able to complete the transaction in question, or, alternatively, need not have been by reason of I.R. Capital's supposed repudiation.

 42      I intend to consider the fundamental question whether I.R. Capital, through its principal, Mr. Rogowski's words and conduct and its solicitor's letter of August 31, 1989, repudiated the agreement of December 12, 1988, as modified orally on June 30, 1989.

 43      Mr. Panton, the recently instructed solicitor for I.R. Capital, first spoke with Mr. Seibold, solicitor for Laredo, on August 23, 1989.  During that conversation the two solicitors came to an understanding on a mechanism for closing the transaction which was somewhat at variance with the closing provisions dictated by Clauses 4, 5, 7 and 8 of the agreement of December 12, 1988.  On August 30, 1989, Mr. Seibold forwarded a letter to Mr. Panton enclosing what he perceived to be all the necessary documents for execution for I.R. Capital to complete the transaction as they had agreed. This letter was not delivered to Mr. Panton until the afternoon of August 31, 1989, due to Mr. Seibold's error in not forwarding the letter to Mr. Panton's correct office address.

 44      What next occurred is the receipt by Mr. Richert of Mr. Rogowski's couriered letter of August 30, 1989, which Mr. Richert received after his return from Hong Kong which I quote again:

What's going on re the deal -- 49 townhouse units to complete August 31, 1989??
Please respond immediately.

 45      The trial judge, at para. 26 of his reasons, made this finding:

 "This was the first time Mr. Richert had any knowledge of the position taken by Mr. Rogowski.  He immediately called Mr. Rogowski and explained his position, that he understood there were another seven days to complete.  This understanding was denied and the 6.4 million dollars was demanded by August 31, 1989, the next day."

 46      The trial judge reviewed two conversations that Mr. Rogowski and Mr. Richert had on the morning of August 31, in para. 27 of his reasons, which I quote:

       On August 31, 1989, the parties met briefly at the job site while Mr. Richert inspected the premises to determine whether or not they were completed.  There was some work being done by a painter, a plumber's truck was there and there were some cleaners.  Just after 9 a.m., they attended at at[sic] Mr. Rogowski's office.  Mr. Richert said that he was ready to complete according to the agreement.  Mr. Rogowski repeated his position that completion would be today; Mr. Richert replied that no, he had 7 more days.  He was shown certain completion certificates from the municipality, but these were not actually final completion certificates.  Mr. Rogowski said the final certificates were at his lawyer's office where they could be picked up, whereupon Mr. Richert said words to the effect of, "I'm not your messenger, send it to me."  Whereupon Mr. Rogowski said words to the effect of,  "Well, if you have not anything more intelligent than that to say, the deal is off." Whereupon Mr. Richert said words to the effect of, "I wish to complete according to the agreement."

 47      The trial judge made further findings of fact in para. 41 of his reasons, which are amply supported by the evidence, limited parts of which I now propose to set out:

       The co-operative stance taken by Mr. Panton soon ended upon the instructions of Mr. Rogowski. On August 30, 1989, Mr. Rogowski spoke to Mr. Panton and told him to insist on closing on August 31, 1989, and to convey to Mr. Seibold that he had no instructions to conclude the matter in any way except as set out in the letter drafted by Mr. Panton (and approved by Mr. Rogowski) and sent on August 31, 1989.  Mr. Panton admits that despite his prior agreed-upon arrangements with Mr. Seibold, the requirements he set out in his August 31, 1989 letter unilaterally altered those arrangements.  The letter sent by Mr. Panton on August 31, 1989, included, in accordance with cl. 5.2.1 of the agreement, an executed transfer of an estate in fee simple.  However, it did not enclose the Form A that had been agreed upon prior, despite the fact that Mr. Panton admitted in cross-examination that without Form A the transfer could not be perfected in the land registry office (about which more will be said later in these reasons).  Part of the August 31, 1989 letter reads as follows:


"We are instructed by our client that your client has indicated that it may not be in a position to complete this transaction today's date.  We wish to confirm that it is our client's position that as a result of the June 30th Agreement the completion of this transaction is to occur on August 31, 1989.  As time is expressed to be of the essence of this Agreement, we must insist that the completion monies in the amount of $6,400,000.00 by way of certified cheque payable to our firm in trust be received in our offices on today's date.

                            . . . In accordance with paragraph 5.2.1 of the Agreement, we are enclosing duly executed Transfers of an Estate in Fee Simple to the subject lands upon your undertaking that upon submission of the transfers to the New Westminster Land Title Office and upon a satisfactory post registration index being obtained, to forward to our offices the net sale proceeds in the amount of $6,400.000.00 on August 31, 1989, and upon your further undertaking that if this transaction cannot close on today's date, that you will return the enclosed documents to our offices immediately upon demand.

We further confirm that should this matter not complete on today's date, it is our client's position that paragraph 6 of the Option Agreement shall govern your client's failure to complete the transaction.


       This letter was delivered to Mr. Siebold shortly after noon on August 31, 1989.

 48      Later in his reasons, in paras. 76 to 78 inclusive, the trial judge made the following findings:

       The letter of August 31, 1988(sic), amounts to a repudiation of the agreement.  This letter in effect provides that if the vendor does not receive the balance of the funds in the sum of $6.4 million by August 31, 1989, then the deal is terminated.

       I have already found that I.R. Capital was not entitled to take that position.

       It was also not able to take that position on August 31, 1989, for another reason, and that is that the closing date for this transaction was September 11, 1989, and not August 31, 1989.

 49      In my judgment, having previously determined on an interpretation of the written agreement as orally modified that Laredo had until September 11, 1989 to complete the purchase of the 49 completed condominium units, I conclude that I.R. Capital's repudiation of the agreement commenced on August 31, 1989, when its solicitor demanded completion that day in its letter to Laredo's solicitor.  The repudiation was a continuing one as the executed transfer documents were demanded to be returned on the next business day.  I.R. Capital was in breach of its agreement with Laredo from August 31 to September 11, 1989, and thereafter in resisting the promptly commenced action for specific performance.  There is nothing to be found in the evidence indicating a willingness by I.R. Capital to keep the transaction alive or, as phrased in the older cases, to keep the agreement afoot.  As Mr. Rogowski announced at the completion of the last conversation he had with Mr. Richert on the morning of August 31, 1989, "the deal is off".

 50      Counsel for I.R. Capital, in addressing the issue whether I.R. Capital had repudiated, made these submissions.

 51      First, in para. 9 of his argument in the appellants factum, in addressing the trial judge's finding that "the letter of August 31, 1989 constituted a repudiation by I.R. Capital of its contractual obligations, and thus a demonstration of a lack of willingness to complete", counsel for I.R. Capital asserts that "at no time did Laredo accept such repudiation;  rather Laredo maintained, beginning on September 20, 1989, a claim for specific performance of the option agreement."

 52      Insofar as that submission goes it is correct that Laredo promptly commenced this action, however the statement of claim issued contemporaneously with the writ of summons on September 20, 1989, claimed in para. (c) of the prayer for relief:

(c)

Damages for the breach of the Option Agreement in lieu of or in addition to specific performance.

 53      Secondly, it was maintained that while on September 13, 1989 Laredo asserted the right to acquire title to all 49 units, it took no active steps either to tender documents or funds or both while in the absence of acceptance of repudiation the contract was still clearly alive.  In fact, Mr. Seibold's letter of August 30, 1989 did tender documents for the completion of the transaction, however it is common ground that at no time did Laredo place the cash portion of the balance of the purchase price after adjustments in trust with its solicitor in compliance with Clause 5.1.  I will later address the issue whether it was required to do so.

 54      Next, counsel for I.R. Capital cited text book authorities for the general proposition that to rely on repudiation to maintain a claim for damages, or return of a deposit, the alleged innocent party must show by words or conduct that it accepted the repudiation.  I am not satisfied that that broad proposition applies to the facts of this case.

 55      Counsel for I.R. Capital then cited and relied upon a passage of the reasons for judgment of Southin, J.A. in Shaw Industries Ltd. v. Greenland Enterprises Ltd. (1991), 54 B.C.L.R. (2d) 264 at 272, where she wrote:

       From the proposition that the contract still subsists, it follows that neither party is relieved of his own contractual obligation to complete by the failure of performance of the other.  He cannot treat that failure as a repudiation.  In order that he may do so, he must himself first give such a notice and must at the time thereby fixed for completion be himself ready, willing and able to perform.

 56      That case is clearly distinquishable from the present.

 57      There neither party exhibited a prior intention not to complete.  The day for completion simply arrived and went without either having done what was required of it in order to complete that day.  In the present case, more than a week before the time for performance arrived, and at a time when the purchaser could not be expected to be ready to close, the vendor demanded performance for which the agreement did not call, and thereafter made it plain that it would not perform in accordance with the agreement.

 58      In the circumstances of the present case the purchaser cannot be required to prove readiness, willingness and ability to perform.  It was known to both parties that the vendor's unwillingness to observe the terms of their agreement, by providing evidence of completion of construction at least a week prior to the date of closing, and insisting instead that the purchase money be paid forthwith on the day of delivery of the certificate, made it impossible for the purchaser to place itself in a position to close, and the vendor was unwilling thereafter to complete their agreement in accordance with its terms.

 59      For the purchaser in this case to have put itself in a position to close in accordance with the agreement would have been an exercise in futility, and its cause of action for damages was complete without the necessity of so doing.

 60      Counsel for I.R. Capital, in para. 23 of the argument in his factum, relied on other excerpts from Shaw Industries Ltd. v. Greenland Enterprises Ltd., supra where Southin, J.A. said at p. 272:

       The underlying reason for this is that a party to a contract for the sale of land, who is in essential default, cannot be heard to complain of the wrongdoing of the other until he has given the other the opportunity to do right and is himself ready to do right.

 61      The short answer to that submission is that on August 31, 1989, when I.R. Capital repudiated its agreement with Laredo, the date for completion had not arrived and the quoted passage has no application to the facts of this case.

 62      Finally, counsel for I.R. Capital submitted in para. 25 of his factum as follows:

"The finding of the learned trial judge to the effect that the respondent 'has the right to maintain an action for damages even although it cannot show that it was ready, willing and able to perform (A.B. 353, ll. 8-10) flies in the face of the Shaw Industries decision and, more particularly, ignores the more basic proposition, namely that while the respondent asserted a claim for specific performance it ought properly to have been able to perform its obligations."

 63      I have previously expressed the view that the principles expressed in Shaw Industries are not directly applicable on the facts as found by the trial judge in this case.  Apposite, in my view, is the judgment of the Supreme Court of Victoria that has been approved by the House of Lord. The two cases I refer to are:  McKenna v. Richey (1950), V.L.R. 360 and Johnson and another v. Agnew (1979), 1 All E.R. 883 (H.L.).  Both decisions were concerned with the position of a plaintiff entitled to a decree of specific performance where due to impossibility of performing the decree, the plaintiffs were permitted to pursue their rights at common law to claim damages where the defendants had repudiated and continued to repudiate the contracts.  The principle therein expressed is apparently applicable equally before as well as after judgment in a specific performance action.  I content myself with a quotation from the speech of Lord Wilberforce, with whom all of the other Law Lords agreed.  He says (at p. 893):

       Then in McKenna v. Richey, a case very similar to the present, it was decided by O'Bryan J in the Supreme Court of Victoria that, after an order for specific performance had been made, which in the event could not be carried into effect, even though this was by reason of delay on the part of the plaintiff, the plaintiff could still come to the court and ask for damages on the basis of an accepted repudiation.  The following passage is illuminating:


'    The apparent inconsistency of a plaintiff suing for specific performance and for common law damages in the alternative arises from the fact that, in order to avoid circuity of action, there is vested in one Court jurisdiction to grant either form of relief. The Plaintiff, in effect, is saying:  "I don't accept your repudiation of the contract but am willing to perform my part of the contract and insist upon your performing your part--but if I cannot successfully insist on your performing your part, I will accept the repudiation and ask for damages."  Until the defendant's repudiation is accepted the contract remains on foot, with all the possible consequences of that fact.  But if, from first to last, the defendant continues unwilling to perform her part of the contract, then, if for any reason the contract cannot be specifically enforced, the plaintiff may, in my opinion, turn round and say:  "Very well, I cannot have specific performance; I will now ask for my alternative remedy of damages at common law."  This, in my opinion, is equally applicable both before and after decree whether the reason for the refusal or the failure of the decree of specific performance is due to inability of the defendant to give any title to the property sold, or to the conduct of the plaintiff which makes it inequitable for the contract to be specifically enforced.'


Later the judge said:


'    It is an appropriate case for a Court of Equity to say:  "As a matter of discretion, this contract should not now be enforced specifically, but, in lieu of the decree of specific performance, the Court will award the plaintiff such damages as have been suffered by her in consequence of the defendant's breach. That is the best justice that can be done in this case."'


The judge in his judgment fully discusses and analyses the English cases but nevertheless reaches this view.

               My Lords, I am happy to follow the latter case.

       (Emphasis added.)

 64      In the case at bar, notwithstanding the first act of repudiation by I.R. Capital on August 31, 1989, Laredo, by commencing action on September 20, 1989 wherein it claimed specific performance and/or damages in lieu thereof, kept the agreement alive "...with all the possible consequences of that fact."  However, I.R. Capital, which was in breach of its duty and obligations under the agreement as amended, never resiled from its position that the transaction had to be completed on August 31, 1989.  The letter from the solicitor for Laredo to the solicitor for I.R. Capital on October 19, 1989, clearly indicated that Laredo would be pursuing its claim for damages, after having decided not to post 1.5 million dollars security. This was the first clear indication that Laredo was electing no longer to pursue its claim to keep the agreement alive, and that thereafter it was pursuing only its common law remedies.

 65      As I have previously noted, nothing done up to or after October 19, 1989 indicated any willingness on the part of I.R. Capital to complete the transaction.  From that date forward it was open to Laredo to claim its alternative remedy at common law for damages.

 66      As a consequence, it is my opinion that since the conduct of I.R. Capital constituted a repudiation, Laredo was not required to place the balance of the purchase price less adjustments in its solicitor's trust account, nor tender documents.

 67      The trial judge said:

       I find that Laredo has the right to maintain an action for damages, even although it cannot show that it was ready, willing and able to perform.

For the reasons previously expressed I agree with that conclusion and need not therefore consider the other arguments advanced by counsel for I.R. Capital under Ground 3.

 68      With respect to Ground 1, namely whether I.R. Capital was ready, willing and able to complete the transaction on August 31, 1989, the trial judge went to considerable length in analyzing the evidence and concluded that I.R. Capital's performance was defective, or in breach of its obligations, in three additional areas.  I am not persuaded that the trial judge has been shown to have been demonstrably in error.  I reject Ground 1 on the basis that I.R. Capital repudiated the agreement as amended.

 69      From that flows the conclusion that I.R. Capital is not entitled to the benefit of Clause 6 of the agreement and that, being itself in default by repudiating the agreement as amended, I.R. Capital must return to Laredo the aggregate option monies paid, namely $700,000, as the trial judge concluded.

 70      I turn now to the fourth ground of appeal and the sole ground of appeal raised by Laredo's cross-appeal.

4.

The Learned Trial Judge erred in finding that the Respondent (Plaintiff) Laredo Development Ltd. was entitled not only to a return of the deposit of $700,000.00 but of $429,000.00.


CROSS APPEAL

       The Learned Trial Judge erred in not awarding Laredo the entire profit of $950,000.00[sic] which he found Laredo would have made.

 71      In the unique circumstances of this case, the trial judge assessed Laredo's damages on the basis of its lost opportunity to sell the 49 condominium units, 3l of which were bound in contract to R.I.A. and 18 of which Laredo would have had to arrange to sell on the open market on and after September 11, 1989.

 72      The trial judge found that the 31 units may have realized $5,150,000 and the other 18 might have sold over a time netting in the order of $2,850,000 for a gross value of $8,000,000.  On the basis of Laredo's purchase price of $7,100,000, that would leave a profit potential of $900,000. The trial judge wrote:

       The above analysis is approximate, and does not allow for various contingencies that may well occur in the marketplace, but it does indicate there was a likelihood that I must value of 31 of the units having ready buyers and the remaining 18 units being able to be sold in the marketplace.

       This exercise is premised on the fact that it was the failure of I.R. Capital that prevented Laredo from completing its contractual arrangements to resell the units, and it is the chance of that successfully completing but for the default of I.R. Capital that is to be valued.

       In all of the circumstances, I am of the opinion that the chance of making a profit if I.R. Capital had performed, is 60 per cent, and accordingly, I award 60 per cent of the profit it would have made had the sale by Laredo been completed to RIA Properties and in turn to the Hong Kong investors.  That is 60 percent of $715,000 or $429,000.

 73      Counsel for I.R. Capital does not take issue with the principles of law applied by the trial judge, but submits that Laredo has failed to prove that it would have been able to complete the transaction securing the chance to earn the profit in the first instance.  Here he submits the trial judge's findings are contrary to the evidence.

 74      I have considered the facts found by the trial judge on this issue and my review satisfies me that there was sufficient evidence to support his conclusions.

 75      Counsel for Laredo, in his factum on the cross-appeal, first submitted that this was not a loss of chance/opportunity case.  If this submission is correct, so the argument goes, the trial judge should have awarded Laredo damages based either its loss of sale to R.I.A., i.e. $7,815,000 - $7,100,000 = $715,000, or the $900,000 loss of profits previously calculated on the basis of the actual sale of 31 units and future sales of 18.  In support of this submission counsel for Laredo referred to a judgment of this Court:  Houweling Nurseries Ltd. v. Fisons Western Corporation (1988), 37 B.C.L.R. (2d) 2.  In that judgment Madam Justice McLachlin, then of this Court, summarized the law in these words at p. 8:

       In my view, the law may be summarized as follows.  The basic rule is that damages for lost profits, like all damages for breach of contract, must be proven on a balance of probabilities.  Where it is shown with some degree of certainty that a specific contract was lost as a result of the breach, with a consequent loss of profit, some should be awarded.  However, damages may also be awarded for loss of more conjectural profits, where the evidence demonstrates the possibility that contracts have been lost because of the breach, and also establishes that it is probable that some of these possible contracts would have materialized, had the breach not occurred.  In such a case, the court should make a moderate award, recognizing that some of the contracts may not have materialized had there been no breach.

       The matter may be put another way.  Even though the plaintiff may not be able to prove with certainty that it would have obtained specific contracts but for the breach, it may be able to establish that the defendant's breach of contract deprived it of the opportunity to obtain such business.  The plaintiff is entitled to compensation for the loss of that opportunity.  But it would be wrong to assess the damages for that lost opportunity as though it were a certainty.

 76      Having reviewed the evidence of Mr. Richert, Mr. Seibold, and the documents relevant to this issue, I am satisfied that there was no justification for awarding damages on the basis of loss of profits on the Laredo-R.I.A. transaction.  There is no evidence in the record to suggest that by September 11, 1989 R.I.A. would have been in a position to complete its agreement with Laredo, paying over $6,815,000 in cash.

 77      The whole scenario quarterbacked by Mr. Seibold was an effort to entice and facilitate 31 Hong Kong purchasers to complete in accordance with their respective interim agreements of purchase and sale which called for completion in many instances on dates subsequent to September 11, 1989. There was a substantial degree of uncertainty in connection with those transaction, as Laredo had no direct contractual rights with those purchasers.  With respect to the 18 unsold units, there was no certainty as to when or for how much those units were going to sell.  Additionally, on the evidence tendered by Laredo, there was nothing to indicate what costs and expenses were to be incurred in effecting those sales or the interest expenses that Laredo would incur until the final unit was sold.  Shortly put, the factual situation and the manner in which the damage claim was put forward demanded an approach to the problem on the basis of lost opportunity and not an assessment of loss on the basis of loss of profits.

 78      Counsel for Laredo's alternate submission is that the trial judge should have used an expected level of profit of $900,000 and a "chance" at greater than 60 percent.  The argument continued that 60 percent was an arbitrary choice because the trial judge did not give an explanation for arriving at the 60 percent figure.  Then inconsistently in para. 15 of Laredo's factum on the cross-appeal it is asserted that the trial judge arrived at 60 percent by finding 31 of the 49 units had been sold through R.I.A. which, according to my calculator, is 63.25 percent.  I pause to say that that was not what the trial judge did.

 79      In my judgment, on the evidence presented to the trial judge, he was faced with substantial uncertainties, contingencies and a lack of evidence on the anticipated future expenses that Laredo could reasonably be expected to realize in selling the 18 remaining units, and the expenses incurred in closing even the original 31 transactions with the Hong Kong purchasers if they all had completed according to their respective agreements.  Faced with the complex situation he was, I consider the trial judge's methodology to be appropriate and cannot say that the 40 percent reduction in loss of a potential profit is wrong.

 80      I address the issue finally by asking myself whether the assessment is inordinately low.  I start from the premise that had R.I.A. completed as anticipated, Laredo would have realized a profit of $715,000 if the two sales had completed as originally anticipated.  Through no fault of I.R. Capital, R.I.A. experienced difficulties in selling the 49 condominium units by the original target date of June 30, 1989, and by August 31, 1989 had only 31 units sold at varying completion dates.  During July and August, 1989, Mr. Richert had travelled to Hong Kong on two occations expending energy, time and money, no doubt, in his efforts to keep the 31 prospective purchasers onside.  Also, from September 11 onward, additional costs, expenses, commissions and legal fees would be incurred -- to say nothing of Mr. Richert's personal involvement which would further erode the profit margin on the I.R. Capital transaction.  Under the circumstances, I am not prepared to say that $429,000 is an inordinately low damage award.

 81      In the result I would dismiss I.R. Capital's appeal and Laredo's cross-appeal.

TOY J.A.
TAYLOR J.A.
:— I agree.
ROWLES J.A.:— I agree.